Aerogel insulation coating is made by mixing aerogel with appropriate solvent and stabilizer. Aerogel insulation coatings have a wide range of applications, which can be used in construction, industrial equipment, aerospace and other fields. It has excellent thermal insulation and fire performance, can effectively reduce the energy consumption of buildings, and provide good thermal insulation effect. In addition, aerogel insulation coatings also have good sound absorption and seismic performance, which can improve the comfort of indoor environment.

绝热保温涂层_气凝胶涂料_技术解决方案-天津华燚

The construction of aerogel insulation coating mainly includes the following steps:
1, basic treatment: Before construction, it is necessary to treat the surface of the basic level, including cleaning, oil removal, ash batch, etc., the basic level must be dry, smooth and free of debris.
2, mixing paint: aerogel insulation paint, solvent and other materials according to the proportion of the instructions to mix, and then stir evenly.
3, paint primer: according to needs, you can first paint a layer of primer, which can enhance the adhesion and stability of the paint.


4, paint construction: Use rollers or spray guns and other tools to paint the mixed aerogel paint on the surface, evenly covering the entire base surface. During construction, it should be carried out from top to bottom, first in detail and then in large area.
5, paint twice: After the first paint dry, then paint once aerogel paint.
6, Finish the surface: when the second layer of paint is dry, you can use sandpaper and other tools to polish the surface to obtain better smoothness and appearance.
7, testing: After curing, the aerogel insulation coating should be tested for appearance, thickness and adhesion. Appearance is smooth and smooth, no other debris, no drum, crack and delamination phenomenon. Dry film thickness should be greater than or equal to the design requirements.
During the construction process, it is necessary to avoid construction in a high humidity or high temperature environment, and maintain good ventilation. At the same time, it is also necessary to do a good job of protection, pay attention to protect the eyes and skin, avoid splashing into the eyes or long-term contact with the skin.